An architectural drawing is a set of instructions. Setting out is the discipline of executing those instructions at full scale, on actual ground, with physical precision. A column shown at grid reference A2 on a structural drawing must be cast at exactly that coordinate β not 50 mm away, not 100 mm. A floor slab must be cast at the specified reduced level, not 30 mm high or low. Setting out errors that pass undetected through foundation stage are locked permanently into the structure β correcting a column position after concrete is poured costs orders of magnitude more than setting it out correctly in the first place. This article explains how professional setting out works, what instruments are used, and why construction projects of any significance should not attempt this process without a qualified engineering surveyor on site.
What Setting Out Actually Means
Setting out β also called staking out or survey control β is the process of establishing physical reference marks on a construction site that correspond to specific points, lines, and levels shown on engineering drawings. These marks guide every trade on site: the concreting crew pouring foundation bases, the steel fixers positioning rebar cages, the formwork carpenters constructing slab shuttering, and the mechanical and electrical engineers installing sleeves and penetrations. Every downstream construction activity depends on the accuracy of the marks the surveyor places before construction begins.
The term covers three distinct but related activities that run throughout a construction project. Horizontal setting out establishes the planimetric positions of structural elements β the X and Y coordinates of column centrelines, wall faces, pile positions, and building corners. Vertical setting out establishes the reduced levels (heights above a defined datum) of foundation bases, slab soffits, finished floor levels, and structural steel bearing levels. As-built verification confirms, after construction of each element, that it was built at the position and level specified β detecting and recording any deviations before the next construction stage is built on top of them.
Setting out is not a one-time event at the start of a project. It is a continuous process that accompanies every construction stage: foundations, ground floor slab, each structural floor, external works, and services installation. A building survey team that only arrives for the initial peg-out and then disappears is not delivering a setting-out service β it is providing a one-day site visit dressed up as engineering survey support.
Reduced Level (RL): height of a point above a defined vertical datum (typically mean sea level in Kenya, or a site benchmark). Temporary Bench Mark (TBM): a permanent, protected reference point on or near the site from which all levels are transferred. Structural grid: the reference coordinate system defined in the structural drawings, usually aligned with the primary structural axes of the building. Offset peg: a peg set at a known distance from a structural line, so that the line itself can be re-established even after excavation or formwork disturbs the original marks.
The Setting-Out Process: Six Stages on Every Project
Before touching an instrument, the setting-out surveyor reviews the full drawing package β architectural, structural, and services β and extracts the coordinates, grid dimensions, levels, and setback distances that define every point to be marked on site. This office work catches drawing errors, inconsistencies between disciplines, and ambiguous references before they become site problems. A structural drawing that shows a column at the intersection of Grid A and Grid 2 is unambiguous in plan β but its absolute position on site depends on where the origin of the structural grid is anchored, and what its orientation is relative to the site boundary or a national coordinate system. If the drawing does not specify this, the surveyor must query the engineer before proceeding. Setting out from an incorrectly interpreted coordinate origin is one of the most common β and most expensive β mistakes on Kenyan construction sites.
The first physical act of setting out is establishing the site's control framework β the small number of permanent, protected reference points from which all subsequent setting out will be performed. Control points are set in locations where they will not be disturbed by construction activity: outside the building footprint, on stable ground, protected by concrete collars or steel covers if necessary. For large sites, a traverse of four to six control points around the perimeter is established, with each point measured relative to its neighbours using a total station to form a closed geometric figure whose internal consistency can be checked. The traverse is then tied to the structural grid origin defined in the drawings.
A Temporary Bench Mark (TBM) is established on or near the site β typically a nail in a concrete kerb, a mark on an existing wall, or a purpose-set steel pin β whose Reduced Level is precisely determined by levelling from the nearest national benchmark (obtained from a Survey of Kenya bench mark list) or from an RTK GNSS observation. All subsequent vertical setting out derives from this TBM. A site with an incorrectly established TBM will have every floor level wrong by the same systematic error β an error that is particularly insidious because it is self-consistent and may not be detected until the building's finished floor level fails to connect correctly with external drainage or access.
With control established, the surveyor sets out the structural grid β the network of reference lines from which all structural element positions are derived. For a reinforced concrete framed building, this means marking the centrelines of every column on the cleared founding level. The total station is set up over a control point, oriented to a second control point, and used to compute and mark the position of each column centreline intersection. A nail driven through a wooden peg at the exact computed position marks the column centreline. Around each column position, four offset pegs are set at a standard distance (typically 500 mm or 1,000 mm) from the centreline in each orthogonal direction. These offsets survive the excavation of pad foundations and the erection of formwork β when the carpenter needs to position the column formwork, they measure from the surviving offset pegs rather than the centreline peg, which may have been disturbed.
For buildings using structural steelwork, the setting out involves positioning holding-down bolts in the concrete base to sub-millimetre precision β the bolt group must match the steel column base plate dimension precisely or the column cannot be erected. This is one of the most demanding setting-out tasks in construction: bolt positions must be maintained within Β±3 mm of design position while the surrounding concrete is poured, using a specially fabricated bolt jig welded to the rebar cage to lock them in position before casting.
Every poured concrete element has a specified Reduced Level that must be achieved within tolerance. Foundation bases must be cast at the specified bearing level (too high and the column sits short; too low and cover to reinforcement is compromised). Slab soffits must be formed at the precise level that delivers the specified floor-to-ceiling height after the slab thickness is added. Finished floor levels must achieve the design gradient for drainage, accessibility, and connection to doorways and external pavements.
Level setting uses a digital level (or optical automatic level) and a levelling staff. The surveyor sets up the level on stable ground, takes a back-sight reading on the TBM to establish the height of instrument (HI), then takes foresight readings at the points to be levelled. The difference between the calculated level and the required RL tells the carpenter, concreting crew, or steel fixer exactly how much to adjust. For slabs, screed rails or level pins are set at the exact finished surface level β the concreting crew screeds to these pins. For high-precision applications (equipment bases, crane rails, prestressed structures), a digital level with a precision staff achieves Β±1 mm accuracy over distances up to 50 m.
Once the ground floor slab is cast, the challenge of setting out changes: the column centrelines on the ground floor are now buried under concrete and rebar or obscured by formwork for the columns above. The structural grid must be transferred vertically to each new floor level. Two methods are used depending on the height and accuracy requirements. For buildings up to approximately 10 storeys, a plumb bob or optical plummet is used: the surveyor positions themselves directly above a ground floor control mark (by cutting a small hole in the slab if necessary at a pre-planned opening) and drops a steel wire with a precision plumb bob to re-establish the control point position on the upper floor. For taller structures β high-rise buildings, towers, and multi-storey car parks β a laser plummet or zenith-pointing total station projects a vertical laser beam upward through designated openings in successive slabs, establishing control at each floor level to Β±2β3 mm over 50 m of height.
Setting out marks where things should go. The as-built survey records where they actually went. After each poured element β foundation bases, columns, beams, slabs β the surveyor measures the actual position and level of the completed work against the design. Deviations are recorded in a formal as-built report and assessed against the specified tolerances. Deviations within tolerance are recorded and passed. Deviations outside tolerance trigger a non-conformance report (NCR), which requires the structural engineer to assess whether the deviation is structurally acceptable, can be remediated, or requires demolition and reconstruction.
This stage is where setting out pays for itself most obviously. A column that is 25 mm out of position is not necessarily structurally critical β but it may clash with a facade element, cause a beam centreline to miss, or misalign a facade grid. Detecting this at the as-built stage, before the next floor is cast, costs a report and a conversation with the engineer. Detecting it six floors later costs a structural assessment, a potential partial demolition, and the contractual consequences of a delayed handover.
The Three Core Instruments
Professional setting out uses three primary instruments, each with specific applications and accuracy characteristics. Understanding what each instrument can and cannot do is essential for specifying the right level of survey support for your project.
Setting-Out Tolerances by Element Type
Tolerances in setting out are not arbitrary β they are derived from the structural engineer's calculations of how much deviation a structural element can sustain before it affects the design load path, and from the architect's requirements for visual and functional alignment of facades, finishes, and openings. The table below gives the standard tolerances applied on Kenyan construction projects, drawn from BS 5606 (Accuracy in Building), the Institution of Structural Engineers guidelines, and NCA (National Construction Authority) requirements.
| Structural Element | Positional Tolerance (Plan) | Level Tolerance (Vertical) | Verticality | Category |
|---|---|---|---|---|
| Column centreline (foundation) | Β±5 mm from design grid | Β±5 mm founding level | H/600 max lean | Structural β Tight |
| Holding-down bolts (steelwork) | Β±3 mm from design | Β±2 mm projection | Β±2 mm group squareness | Structural β Tight |
| Pile positions (driven/bored) | Β±75 mm (isolated) Β· Β±25 mm (group) | Β±50 mm cut-off level | 1:75 max rake | Structural β Standard |
| Slab soffit level | n/a | Β±5 mm from design RL | n/a | Structural β Tight |
| Finished floor level (concrete) | Β±5 mm surface flatness | Β±10 mm from design RL | n/a | Finish β Standard |
| Wall line (structural block/RC) | Β±10 mm from design | Β±5 mm at each storey | H/500 per storey | Structural β Standard |
| Road formation level | n/a | Β±15 mm from design | n/a | Civil β Loose |
| Earthworks bulk cut/fill | Β±100 mm plan | Β±25β50 mm level | n/a | Civil β Loose |
| Equipment bases (machinery) | Β±2 mm from design | Β±1 mm from design RL | Β±0.5 mm/m flatness | Precision β Very Tight |
Six Setting-Out Errors That Cause Real Construction Problems
On a 12-storey affordable housing block in Nairobi, Geopin was engaged for setting out and as-built verification from foundation stage. At the third-floor level, as-built measurements of the column grid revealed a systematic offset β all columns on grid line C were consistently 22 mm north of their design positions. Investigation traced the error to the original setting-out, where the structural grid had been established from a control peg that had been disturbed and re-installed approximately 22 mm from its original position without the disturbance being detected. The engineer assessed the deviation and confirmed it was structurally acceptable without remediation β but required an adjustment to the pre-cast facade panel dimensions for grid line C. The cost of the as-built detection and engineering assessment: approximately KES 280,000. The cost of discovering the same deviation at the eleventh floor via a facade panel that no longer fits its opening: structurally and contractually incalculable.
Construction Setting Out and As-Built Surveys Across Kenya
Geopin's engineering survey team provides full-stage setting out, level control, structural grid transfer, and as-built verification for construction projects of all scales β from single residential buildings to multi-storey commercial developments.
Enquire About Engineering Surveys β