An architectural drawing is a set of instructions. Setting out is the discipline of executing those instructions at full scale, on actual ground, with physical precision. A column shown at grid reference A2 on a structural drawing must be cast at exactly that coordinate β€” not 50 mm away, not 100 mm. A floor slab must be cast at the specified reduced level, not 30 mm high or low. Setting out errors that pass undetected through foundation stage are locked permanently into the structure β€” correcting a column position after concrete is poured costs orders of magnitude more than setting it out correctly in the first place. This article explains how professional setting out works, what instruments are used, and why construction projects of any significance should not attempt this process without a qualified engineering surveyor on site.

Β±5 mm
Typical positional tolerance for column centrelines
Β±3 mm
Level tolerance for slab soffit and finished floor
1:10,000
Angular accuracy of a survey-grade total station
100Γ—
Cost multiplier β€” correcting a setting-out error after casting

What Setting Out Actually Means

Setting out β€” also called staking out or survey control β€” is the process of establishing physical reference marks on a construction site that correspond to specific points, lines, and levels shown on engineering drawings. These marks guide every trade on site: the concreting crew pouring foundation bases, the steel fixers positioning rebar cages, the formwork carpenters constructing slab shuttering, and the mechanical and electrical engineers installing sleeves and penetrations. Every downstream construction activity depends on the accuracy of the marks the surveyor places before construction begins.

The term covers three distinct but related activities that run throughout a construction project. Horizontal setting out establishes the planimetric positions of structural elements β€” the X and Y coordinates of column centrelines, wall faces, pile positions, and building corners. Vertical setting out establishes the reduced levels (heights above a defined datum) of foundation bases, slab soffits, finished floor levels, and structural steel bearing levels. As-built verification confirms, after construction of each element, that it was built at the position and level specified β€” detecting and recording any deviations before the next construction stage is built on top of them.

Setting out is not a one-time event at the start of a project. It is a continuous process that accompanies every construction stage: foundations, ground floor slab, each structural floor, external works, and services installation. A building survey team that only arrives for the initial peg-out and then disappears is not delivering a setting-out service β€” it is providing a one-day site visit dressed up as engineering survey support.

πŸ“ Key Terminology

Reduced Level (RL): height of a point above a defined vertical datum (typically mean sea level in Kenya, or a site benchmark). Temporary Bench Mark (TBM): a permanent, protected reference point on or near the site from which all levels are transferred. Structural grid: the reference coordinate system defined in the structural drawings, usually aligned with the primary structural axes of the building. Offset peg: a peg set at a known distance from a structural line, so that the line itself can be re-established even after excavation or formwork disturbs the original marks.

The Setting-Out Process: Six Stages on Every Project

Stage 01 πŸ“„
Drawing Review and Coordinate Extraction
Office Β· Before Any Site Work

Before touching an instrument, the setting-out surveyor reviews the full drawing package β€” architectural, structural, and services β€” and extracts the coordinates, grid dimensions, levels, and setback distances that define every point to be marked on site. This office work catches drawing errors, inconsistencies between disciplines, and ambiguous references before they become site problems. A structural drawing that shows a column at the intersection of Grid A and Grid 2 is unambiguous in plan β€” but its absolute position on site depends on where the origin of the structural grid is anchored, and what its orientation is relative to the site boundary or a national coordinate system. If the drawing does not specify this, the surveyor must query the engineer before proceeding. Setting out from an incorrectly interpreted coordinate origin is one of the most common β€” and most expensive β€” mistakes on Kenyan construction sites.

Drawing check Grid origin definition Level datum identification Clash detection RFI to engineer if unclear
Stage 02 πŸ“
Establishing the Site Control Network and Bench Mark
Field Β· First Day on Site

The first physical act of setting out is establishing the site's control framework β€” the small number of permanent, protected reference points from which all subsequent setting out will be performed. Control points are set in locations where they will not be disturbed by construction activity: outside the building footprint, on stable ground, protected by concrete collars or steel covers if necessary. For large sites, a traverse of four to six control points around the perimeter is established, with each point measured relative to its neighbours using a total station to form a closed geometric figure whose internal consistency can be checked. The traverse is then tied to the structural grid origin defined in the drawings.

A Temporary Bench Mark (TBM) is established on or near the site β€” typically a nail in a concrete kerb, a mark on an existing wall, or a purpose-set steel pin β€” whose Reduced Level is precisely determined by levelling from the nearest national benchmark (obtained from a Survey of Kenya bench mark list) or from an RTK GNSS observation. All subsequent vertical setting out derives from this TBM. A site with an incorrectly established TBM will have every floor level wrong by the same systematic error β€” an error that is particularly insidious because it is self-consistent and may not be detected until the building's finished floor level fails to connect correctly with external drainage or access.

Traverse control TBM establishment National benchmark link RTK GNSS tie-in Control schedule document
Typical Control Network Specifications β€” Kenya
Horizontal position accuracyΒ±5–10 mm
TBM level accuracyΒ±3–5 mm from national BM
Traverse closure1:10,000 angular Β· Β±10 mm linear
Control point protectionConcrete collar + steel pin
Minimum control points4 for small site Β· 6–12 large site
Stage 03 πŸ“
Structural Grid Setting Out β€” Columns and Walls
Field Β· Preceding Each Foundation Stage

With control established, the surveyor sets out the structural grid β€” the network of reference lines from which all structural element positions are derived. For a reinforced concrete framed building, this means marking the centrelines of every column on the cleared founding level. The total station is set up over a control point, oriented to a second control point, and used to compute and mark the position of each column centreline intersection. A nail driven through a wooden peg at the exact computed position marks the column centreline. Around each column position, four offset pegs are set at a standard distance (typically 500 mm or 1,000 mm) from the centreline in each orthogonal direction. These offsets survive the excavation of pad foundations and the erection of formwork β€” when the carpenter needs to position the column formwork, they measure from the surviving offset pegs rather than the centreline peg, which may have been disturbed.

For buildings using structural steelwork, the setting out involves positioning holding-down bolts in the concrete base to sub-millimetre precision β€” the bolt group must match the steel column base plate dimension precisely or the column cannot be erected. This is one of the most demanding setting-out tasks in construction: bolt positions must be maintained within Β±3 mm of design position while the surrounding concrete is poured, using a specially fabricated bolt jig welded to the rebar cage to lock them in position before casting.

Total station traverse Column centrelines Offset pegs Β· 1,000 mm Holding-down bolts Β±5 mm tolerance
Stage 04 πŸ“
Level Setting β€” Foundations, Slabs, and Finished Floors
Field Β· Every Poured Element

Every poured concrete element has a specified Reduced Level that must be achieved within tolerance. Foundation bases must be cast at the specified bearing level (too high and the column sits short; too low and cover to reinforcement is compromised). Slab soffits must be formed at the precise level that delivers the specified floor-to-ceiling height after the slab thickness is added. Finished floor levels must achieve the design gradient for drainage, accessibility, and connection to doorways and external pavements.

Level setting uses a digital level (or optical automatic level) and a levelling staff. The surveyor sets up the level on stable ground, takes a back-sight reading on the TBM to establish the height of instrument (HI), then takes foresight readings at the points to be levelled. The difference between the calculated level and the required RL tells the carpenter, concreting crew, or steel fixer exactly how much to adjust. For slabs, screed rails or level pins are set at the exact finished surface level β€” the concreting crew screeds to these pins. For high-precision applications (equipment bases, crane rails, prestressed structures), a digital level with a precision staff achieves Β±1 mm accuracy over distances up to 50 m.

Digital level + staff Back-sight / foresight Level pins for screed HI computation Β±3 mm slab tolerance
Stage 05 πŸ—οΈ
Transfer of Grid to Upper Floors β€” Plumbing and Laser
Field Β· Each Successive Structural Floor

Once the ground floor slab is cast, the challenge of setting out changes: the column centrelines on the ground floor are now buried under concrete and rebar or obscured by formwork for the columns above. The structural grid must be transferred vertically to each new floor level. Two methods are used depending on the height and accuracy requirements. For buildings up to approximately 10 storeys, a plumb bob or optical plummet is used: the surveyor positions themselves directly above a ground floor control mark (by cutting a small hole in the slab if necessary at a pre-planned opening) and drops a steel wire with a precision plumb bob to re-establish the control point position on the upper floor. For taller structures β€” high-rise buildings, towers, and multi-storey car parks β€” a laser plummet or zenith-pointing total station projects a vertical laser beam upward through designated openings in successive slabs, establishing control at each floor level to Β±2–3 mm over 50 m of height.

Optical plummet Laser plummet Slab opening co-ordination Floor-to-floor level transfer Verticality check
Stage 06 βœ…
As-Built Survey β€” Verifying What Was Actually Built
Field Β· After Each Stage Β· Before Next Stage Begins

Setting out marks where things should go. The as-built survey records where they actually went. After each poured element β€” foundation bases, columns, beams, slabs β€” the surveyor measures the actual position and level of the completed work against the design. Deviations are recorded in a formal as-built report and assessed against the specified tolerances. Deviations within tolerance are recorded and passed. Deviations outside tolerance trigger a non-conformance report (NCR), which requires the structural engineer to assess whether the deviation is structurally acceptable, can be remediated, or requires demolition and reconstruction.

This stage is where setting out pays for itself most obviously. A column that is 25 mm out of position is not necessarily structurally critical β€” but it may clash with a facade element, cause a beam centreline to miss, or misalign a facade grid. Detecting this at the as-built stage, before the next floor is cast, costs a report and a conversation with the engineer. Detecting it six floors later costs a structural assessment, a potential partial demolition, and the contractual consequences of a delayed handover.

As-built measurements Deviation from design NCR documentation Engineer sign-off Stage completion certificate

The Three Core Instruments

Professional setting out uses three primary instruments, each with specific applications and accuracy characteristics. Understanding what each instrument can and cannot do is essential for specifying the right level of survey support for your project.

πŸ”­
Total Station
Horizontal + Vertical Position Β· 3D Control
A robotic or manual electronic theodolite combined with an electronic distance measurer (EDM). Measures angles to 1" (1/3600 of a degree) and distances to Β±1–2 mm over typical site distances. The primary instrument for setting out column centrelines, wall positions, pile locations, and any point requiring precise plan position. Sets up over a known control point, back-sights to a second control point to orient itself, and then computes and marks any required position from the project coordinate system.
Angular accuracy: 1"–5" (1/3600–1/720 degree) Distance accuracy: Β±(1 mm + 1.5 ppm) Application: Column/pile positions, grid lines, walls Limitation: Requires clear line of sight to prism or reflector
πŸ“Š
Digital Level
Vertical Control Β· RL Transfer Β· Slab Levels
An automatic or digital optical level that provides precise height measurements when used with a graduated levelling staff. The instrument automatically corrects for any residual tilt after setup, giving consistent accuracy regardless of the operator's levelling skill. A digital level with a barcode staff reads the staff automatically to Β±0.3 mm per reading β€” enabling slab levels and foundation casting levels to be set with confidence. Used for all work requiring precise vertical control: TBM establishment, slab level pins, screed rails, equipment base levels.
Accuracy: Β±0.3–1.0 mm per km of double-run levelling Application: TBM, slab levels, foundation bases, screed rails Equipment: Leica NA700 / Trimble DiNi series typical Limitation: Horizontal only β€” no plan position capability
πŸ“‘
RTK GNSS
3D Position Β· Large Sites Β· Control Establishment
Real-Time Kinematic GNSS provides 3D position (Easting, Northing, Elevation) in real time by comparing the rover receiver's position to a fixed base station. On large construction sites β€” road projects, dam foundations, infrastructure works β€” RTK GNSS enables a single operator to set out pegs across a wide area without the line-of-sight constraints of a total station. Horizontal accuracy of Β±10–20 mm and vertical accuracy of Β±20–30 mm is typical in open conditions. Suitable for earthworks control, road alignment, and large-area infrastructure but not precise enough for structural column positions where Β±5 mm is required.
Horizontal accuracy: Β±10–20 mm (open sky) Vertical accuracy: Β±20–30 mm Application: Earthworks, road alignment, large-area control Limitation: Insufficient for structural column setting out (Β±5 mm req.)

Setting-Out Tolerances by Element Type

Tolerances in setting out are not arbitrary β€” they are derived from the structural engineer's calculations of how much deviation a structural element can sustain before it affects the design load path, and from the architect's requirements for visual and functional alignment of facades, finishes, and openings. The table below gives the standard tolerances applied on Kenyan construction projects, drawn from BS 5606 (Accuracy in Building), the Institution of Structural Engineers guidelines, and NCA (National Construction Authority) requirements.

Structural Element Positional Tolerance (Plan) Level Tolerance (Vertical) Verticality Category
Column centreline (foundation) Β±5 mm from design grid Β±5 mm founding level H/600 max lean Structural β€” Tight
Holding-down bolts (steelwork) Β±3 mm from design Β±2 mm projection Β±2 mm group squareness Structural β€” Tight
Pile positions (driven/bored) Β±75 mm (isolated) Β· Β±25 mm (group) Β±50 mm cut-off level 1:75 max rake Structural β€” Standard
Slab soffit level n/a Β±5 mm from design RL n/a Structural β€” Tight
Finished floor level (concrete) Β±5 mm surface flatness Β±10 mm from design RL n/a Finish β€” Standard
Wall line (structural block/RC) Β±10 mm from design Β±5 mm at each storey H/500 per storey Structural β€” Standard
Road formation level n/a Β±15 mm from design n/a Civil β€” Loose
Earthworks bulk cut/fill Β±100 mm plan Β±25–50 mm level n/a Civil β€” Loose
Equipment bases (machinery) Β±2 mm from design Β±1 mm from design RL Β±0.5 mm/m flatness Precision β€” Very Tight

Six Setting-Out Errors That Cause Real Construction Problems

Error 01
Wrong Grid Origin or Orientation
The structural drawings define a grid, but the drawings do not always clearly state where the grid's origin is in the real world, or what angle the grid makes to true north or the site boundary. If the surveyor assumes an orientation that differs from the engineer's intention by even 0.5Β°, a 50-metre building ends up with its far corner 435 mm out of position. Always obtain written confirmation of the grid origin coordinates and orientation angle before setting out begins.
Error 02
Wrong Datum for TBM
If the site TBM is established from an incorrect national benchmark β€” because the wrong benchmark was identified on the bench mark list, or its stated RL has been affected by ground movement since publication β€” every level on site is systematically wrong by the error amount. A 30 mm error in TBM level translates into every floor slab being cast 30 mm too high or too low β€” which may only become apparent when the building's finished floor level fails to connect correctly with external drainage or neighbouring buildings.
Error 03
Undiscovered Drawing Discrepancy
Architectural and structural drawings for the same building sometimes contain small inconsistencies β€” a wall that is 150 mm on the architectural plan but not dimensioned on the structural drawing, or a column shown at different coordinates on the foundation plan and the first-floor plan. Setting out from the wrong drawing, or from one drawing without checking against the other, produces structures that do not align between floors. A thorough drawing check before site work is not optional: it is where the surveyor earns their fee before picking up an instrument.
Error 04
Disturbed Control Points
Setting-out control pegs that are not adequately protected are routinely disturbed by plant, vehicles, excavation, and the general entropy of a construction site. A surveyor who re-occupies a disturbed control point without detecting the disturbance will set out from an incorrect position. All control points must be protected (concrete collars, safety barriers, clear marking) and independently checked β€” by measurement back to another control point β€” at the start of every setting-out session after any period of site activity.
Error 05
Setting Out Without Offset Pegs
Marking only the column centreline position without setting offset pegs is an incomplete setting out. The centreline peg is inevitably destroyed during excavation and formwork construction β€” and without offsets, the position can only be re-established by occupying the total station again. On a busy site where the surveyor is not permanently on site, this means carpenters positioning column kickers and formwork without a reliable reference β€” a recipe for systematic position errors that compound floor by floor.
Error 06
No As-Built Verification Before Next Pour
The most common omission on Kenyan construction projects is the failure to check the position and level of completed work before the next element is built on top of it. A column base that was cast 18 mm out of position can, in many cases, be accommodated in the column design β€” but only if it is discovered before the column is cast. Discovered after the first-floor slab is poured, the structural implication has already been locked into the building. Routine as-built checks before each stage proceed are not an additional cost β€” they are insurance against far larger costs downstream.
Setting out is the least visible work on a construction site β€” and the most consequential. Everything built above ground depends on the accuracy of the marks placed before the first concrete is poured.
πŸ—οΈ From the Geopin Field Β· Affordable Housing Project, Nairobi

On a 12-storey affordable housing block in Nairobi, Geopin was engaged for setting out and as-built verification from foundation stage. At the third-floor level, as-built measurements of the column grid revealed a systematic offset β€” all columns on grid line C were consistently 22 mm north of their design positions. Investigation traced the error to the original setting-out, where the structural grid had been established from a control peg that had been disturbed and re-installed approximately 22 mm from its original position without the disturbance being detected. The engineer assessed the deviation and confirmed it was structurally acceptable without remediation β€” but required an adjustment to the pre-cast facade panel dimensions for grid line C. The cost of the as-built detection and engineering assessment: approximately KES 280,000. The cost of discovering the same deviation at the eleventh floor via a facade panel that no longer fits its opening: structurally and contractually incalculable.

Professional Setting-Out Services

Construction Setting Out and As-Built Surveys Across Kenya

Geopin's engineering survey team provides full-stage setting out, level control, structural grid transfer, and as-built verification for construction projects of all scales β€” from single residential buildings to multi-storey commercial developments.

Enquire About Engineering Surveys β†’
About the Author
GC
Geopin Consult Engineering Survey Team
ISK Registered Β· Nairobi, Kenya

Geopin's engineering survey team delivers construction setting out, structural grid control, level setting, and as-built verification for residential, commercial, and infrastructure projects across Kenya. Our surveyors are on site before the first concrete is poured and present at every critical pour β€” because setting-out accuracy is not a one-day service.